MBA pavilion refurbishment: Project Works continue (adjourned accordingly)

by Bernard Vassallo

The project works related with the second phase of the MBA pavilion refurbishment continued in the last days.

The 2nd phase of the Ta Qali Basketball Pavilion Renovation Project will consist of the construction of the Spectator Stands and other Facilities within the Ta’ Qali Basketball Pavilion.
This project will see a major upgrade of the basketball facilities. and is being carried out with the assistance from the Government of Malta through SportMalta.

My aim is to lead all through the various stages of this project, right from the start to the end of it which should lead to a completely new environment for the fans and the local game in general.

The below photos and video refer to the works presently going on at the moment

12th November

The second phase of the renovation project is nearing its end and basketball can finally return to its original home, albeit now with a different environment for the fans and enthusiasts following the games.
In my honest opinion, this will be a new era for the Ta Qali Basketball Pavilion.
Below are some photos from the present works:

22nd October (adjourned)

12th September

25th August 2020 (Adjourned)

The 2nd phase will consist of the construction of the Spectator Stands and other Facilities within the Ta’ Qali Basketball Pavilion. This project will see a major upgrade of the basketball facilities.

The below photos and video refer to the works presently going on at the moment

12th August 2020 (adjourned)

The project is presently in its week 8 and the below photos indicate some of the works presently going on at the moment.

4th August 2020 (adjourned)

The project is presently in its week 7 and the below photos indicate some of the works presently going on at the moment.

21st July 2020 (adjourned)

The 2nd phase will consist of the construction of the Spectator Stands and other Facilities within the Ta’ Qali Basketball Pavilion. This project will see a major upgrade of the basketball facilities.

The below photos indicate some of the works presently going on at the moment.

17th July

As already stated some weeks ago, the 2nd phase will consist of the construction of the Spectator Stands and other Facilities within the Ta’ Qali Basketball Pavilion. This project will see a major upgrade of the basketball facilities.

The photos above show part of the works being carried out at the moment in ta Qali.